(click photos for larger view)

10/6/2006
The last parts of the filter building wall are getting formed up and the backfilling around the north side of the filter building has begun as shown here by the backed dirt in the foreground of the photo. |

10/6/2006
Workers have done the first pours on the floor of the basement level of the filter building. |

10/13/2006
Crews have prepared the last part of the floor area in the filter building for a concrete pour. Crews are also forming the sides of formations for the poured in place floor that will cover this lower portion of the filter building. |

10/13/2006
This picture shows one of the large water pits that will help in the treatment and recirculation of the water parks water. |

10/13/2006
Crews are forming up the framing work that will help build the roof to the underground level of the filter building. The roof will be made of poured in place concrete. |

10/20/2006
Crews have finished pouring the floor of the basement level of the filter building. |

10/20/2006
The massive high rate sand filters have arrived on site and will soon be placed inside the filter building. These sand filters clean the water from the pool as it reciruculate's. |

10/27/2006
The crews begin putting together the framing structure for the poured in place roof on the basement level of the filter building. |

10/27/2006
A look inside the control building where several series of conduit have been run that will control the features of the indoor and outdoor water parks. |
June Photos
July Photos
September Photos
October Photos
November Photos
December Photos
February Photos
May 2007 Photos |
|
|
More Photos: Waterpark Indoor Waterpark Golf Course Sunrise Pointe Filter Building Great Lawn Aerial Professional Webcams
|