July 8, 2007

The water park is going great guns. Through the first 15 days of operation, attendance has exceeded 14,000 people. Everyone seems to be thrilled with the facility. If you haven’t seen it, stop by for a free tour.

Work on the indoor water park is progressing well. All the concrete work has been finished; the large play structure has been installed, painting will begin this week. The climbing wall and sprayground will be installed this week.

The hotel parking lot will be finished in the next few days, then work on the beach wall and playground wall will ramp up.

The administrative offices in the hotel are nearly completed. Some staff will move from the temporary office to these offices this week.

The remainder of the kitchen equipment will be installed this week. Walk-in coolers and freezers will be operational this week.

We hope to have the golf course open for play by around mid July.

Mike Wilson
Project Manager, Project AWAYSIS