Click photos for a larger view
9/01/2006
This picture shows the lake side of the east end of the lodge (looking west) showing the basement walkout level of rooms and the three upper floors prior to the placement of the roofing components. |
9/01/2006
As shown in this picture the electrical and plumbing subcontractors are following the framing contractors installing the rough-ins of the plumbing and electrical systems in the facility. |

9/01/2006
This picture is looking west on the basement level of the lodge from the framed east end showing the middle and western sections of the lodge that are now covered with metal sheeting which will eventually support concrete floors in the upcoming weeks. The star effect is provided by the sun shinning through the holes in the metal decking. |

9/01/2006
This picture shows the beginning formation of the middle and western sections of the Kings Pointe facility with the metal decking. Directly in the foreground of the photo is the lobby of the hotel. |

9/01/2006
Crews are installing the western elevator shaft that will service the hotel on the west end near the future development of the indoor waterpark. |

9/15/2006
Crews are preparing the floor area of an area of the conference space and pre-function area of the King’s Pointe Resort. In the foreground of the picture are areas where contractors have dug out the footings for the entrance of the hotel. |

9/15/2006
Shot of the floor of the kitchen area of the lodge which is prepared for a concrete pour shortly after this picture was taken. The blue squares in the floor are the areas where plumbing piping runs up from the basement level of the facility.
|

9/15/2006
This picture is looking east from the eventual seating area of the restaurant at the facility. The picture shows the rooms on the east third of the building where some of the waterproofing material has been rolled on (white paper material). |

9/15/2006
Crews have begun the installation of the gutter system in order to proceed the work done by the roofing contractor who will follow behind shortly after this work is completed. |

9/15/2006
Electricians are working inside the east third of the building installing the beginnings of the electrical system, the contractors refer to it as the electrical “rough in”. |

9/26/2006
A construction worker works on the finishing touches to a concrete pour for the entrance of King’s Pointe Resort |
May Photos
June Photos
July Photos
August Photos
September Photos
October Photos
November Photos
December Photos
January Photos February Photos March Photos May '07 Photos
June '07 Photos
July '07 Photos
August '07 Photos |
Waterpark Photos Golf Course Photos Filter Building Photos Aerial Photos Webcams
|