Storm Lake Iowa Project Awaysis


(click photos for larger view)

07/02/2006
The outside walls of the diving well on the main pool are getting closer to being pour as the final rebar has been added and crews have started putting up the wood forms for the walls.

07/02/2006
The pool contractor has started forming up the walls of the kids play area in the southwest corner of the outdoor pool, shown here with the beginnings of the rebar sticking up from the poured footings.

07/02/2006
Excavation on the lazy river continues to move along with this picture also showing the beginnings of work on forming up one of the main drains on the lazy river in the center of the frame.

7/7/2006
Crews are doing the final framing on one of the lazy river main drains prior to pouring concrete in the frames.

7/21/2006
Framing work on the kids play area of the pool is beginning to take shape.  The kids play area will feature interactive play features, a family slide, a small tube slide, and a separate covered toddler play area.

7/21/2006
The north east corner of the lap lane area is almost ready for the forms to be set up and the walls to be poured for the pool.  This picture is looking south with the walls of the diving wells on the left.


7/21/2006
This picture shows the framing for the north walls of the outdoor pool and two concrete pillars which will have the water walk netting hanging from them when the pool is complete.


7/21/2006
The walls of the diving well have been poured and the floor and walls now give a perspective of just how deep the well is.



7/21/2006
Work is moving right along in the lazy river area of the pool with sub-base being placed and the underground piping put down. 

7/21/2006
This picture show the first pour of floor on the lazy river.  The contractor sprinkles the poured floor to ensure that the concrete hardens in a slow manner to prevent cracking.

7/21/2006
Additional areas of the flooring for the lazy river and some of the side walls are framed up and getting prepared for pouring.  The pipes sticking up out of the rebar will be the pipes that create the flow to the lazy river, similar installations will be done in other areas of the lazy river.

7/21/2006
A little closer shot of the pour floor section of the lazy river.  Also in this picture you can see the excavation done for the plunge well of the vortex bowl slide.

May Photos

June Photos

July Photos

August Photos

September Photos

October Photos

November Photos

December Photos

January Photos

February Photos

March Photos

May 2007 Photos

June 2007 Photos


 

More Photos:   Waterpark   Indoor Waterpark   Golf Course   Sunrise Pointe   Filter Building   Aerial   Professional   Webcams